OBC Part 9 vs Part 3: When a Multiplex Triggers the Larger Building Code

The Ontario Building Code thresholds that move a multiplex from Part 9 to Part 3, what Part 3 adds in sprinklers, exits and cladding, and how it changes design and cost.

By The Multiplex Toronto Builders Crew 6 min read

Four-storey sixplex exterior with non-combustible cladding on a Toronto street

Two Rulebooks in One Code

The Ontario Building Code has two main paths for residential buildings. Part 9 covers houses and small buildings. Part 3 covers larger and more complex buildings. Understanding OBC Part 9 vs Part 3 for a multiplex matters because it is one of the biggest cost switches in the whole project. A fourplex that stays in Part 9 and a sixplex that crosses into Part 3 can differ by six figures before you count the extra two units.

Sprinkler heads in the ceiling of a finished multiplex corridor

This guide explains the thresholds and what changes. It is general information. Your designer confirms the code path for your building. For sixplex projects, see our sixplex construction service.

The two triggers

A residential building generally falls under Part 3 when it exceeds 600 square metres of building area or three storeys in building height. Cross either line and the rules change.

What Part 9 Covers

Part 9 is written for small buildings: houses, semis, rows and small multi-unit buildings within the size and height limits. It uses prescriptive rules, meaning tables and set requirements a BCIN-qualified designer can apply directly. Most Toronto triplexes and fourplexes are Part 9 buildings. They still need fire separations between units, interconnected alarms, egress and sound separation, but they usually do not need sprinklers.

What Part 3 Adds

ItemPart 9 multiplexPart 3 multiplex
DesignerBCIN-qualified designerOAA architect plus engineers
SprinklersUsually not requiredTypically required (often NFPA 13R)
StandpipeNoSometimes
ExitsEach unit’s exit, egress windowsSecond exit or protected exit stairs
Fire alarmInterconnected smoke and CO alarmsOften a fire alarm system
CladdingCombustible cladding commonNon-combustible requirements in some cases
AccessibilityLimited requirementsBarrier-free requirements may apply
Design approachPrescriptiveEngineered, more analysis

Cost and Design Impact

Part 3 affects cost in several ways:

  • Sprinkler system: design, piping, heads, a water service big enough to feed it and annual inspections
  • Second exit: an exterior or interior exit stair that takes floor area or yard space
  • Professional fees: architect and engineering fees run higher
  • Materials: non-combustible cladding where required
  • Schedule: longer permit review and construction

It also affects design. An exit stair can eat into setbacks and soft landscaping. A larger water service for sprinklers may need a bigger lateral from the street. Accessibility requirements may shape the ground floor.

When Part 3 Is Worth It

In the Toronto and East York District and Scarborough Ward 23 North, a sixplex can earn back the Part 3 costs with two extra rent streams, and six units clear the five-unit threshold for CMHC MLI Select financing. On a good lot, that math often works.

When it does not:

  • The lot is tight and the exit stair forces small units
  • The water service cannot support sprinklers without a costly upgrade
  • Rents for the area do not cover the extra cost per unit

In those cases, a Part 9 fourplex, or a fourplex plus garden suite, may deliver a better return.

Staying in Part 9 on Purpose

Some owners design to stay under the triggers: three storeys or less and under 600 square metres. That might mean a fourplex with generous units instead of a cramped sixplex, or a sixplex that is impossible to fit within Part 9 limits and therefore gets dropped. The decision should be made at concept, before the drawings commit you to one path.

Who Designs Each

A BCIN-qualified designer can design within Part 9. Once a building falls under Part 3, an OAA architect must lead. Starting a Part 3 building with a Part 9 designer is a common and expensive mistake, covered in our guide on architect vs BCIN designer.

East York Sixplex Lots

East York sits inside the Toronto and East York District, so six units can be permitted. Many lots there are wartime and post-war parcels, some on ravine edges near Taylor Creek. On East York sixplex lots, Part 3 sprinkler costs and exit layout are usually the deciding factors in whether six units beat four.

Checking Your Own Design Against the Triggers

You can do a rough check of where your design sits before a designer confirms it. Two numbers matter: building area and building height in storeys.

Building area is generally the largest horizontal area of the building above grade, measured to the outside of the exterior walls. It is not the total floor area of all storeys added together. A three-storey building with a 200 square metre footprint has a building area of about 200 square metres, even though its total floor area is about 600.

Building height in storeys counts the storeys above grade. Basements that are mostly below grade often do not count as a storey, but the exact rule depends on how far the basement sits above the ground around it.

DesignBuilding areaStoreysLikely path
Stacked fourplex, 3 storeys + basementUnder 600 sq m3Part 9
Side-by-side fourplex, 3 storeysUnder 600 sq m3Part 9
Sixplex, 4 storeysUnder 600 sq m4Part 3
Large sixplex, 3 storeys, big footprintOver 600 sq m3Part 3

This is a simplified guide. Grade conditions, mezzanines and lofts can change how storeys are counted, and other code provisions may apply to your design. Your designer confirms the path formally.

Why the Check Matters Early

If a concept is close to a trigger, small changes can keep it in Part 9: a lower roof form, a smaller footprint or a basement set lower in the ground. Those changes are cheap at concept and expensive later. If the design clearly belongs in Part 3, it is better to bring in the architect at the start rather than redesign halfway through.

Decide Early

Run the Part 9 vs Part 3 test at feasibility, with costs for both paths. If you want that comparison for your lot, scope your building code path with us before design starts.

Quick Answers

Frequently Asked Questions

When does a multiplex move to Part 3?

When the building exceeds 600 square metres of building area or three storeys in building height. Most sixplexes cross at least one of those limits.

Does Part 3 require sprinklers?

Typically yes for residential buildings of this type, along with other fire protection and egress upgrades. The exact requirements depend on the building's size and design.

Who can design a Part 3 building?

An OAA-licensed architect, working with structural, mechanical and fire protection engineers. A BCIN designer is limited to Part 9.